Rahim, Nur Syafika Artika (2020) Improvement measures of cost overruns in residential construction project in Malaysia. Masters thesis, Universiti Teknologi Malaysia, Faculty of Engineering - School of Civil Engineering.
|
PDF
389kB |
Official URL: http://dms.library.utm.my:8080/vital/access/manage...
Abstract
Cost overrun is the major issue in residential construction project industry worldwide, including Malaysia. These studies therefore aim to achieve three objectives namely: (1) to identify the existing practice for cost control in residential construction project; (2) to investigate the causes of cost overrun in residential construction project in Malaysia; (3) to propose improvement measures on cost overrun in residential construction project in Malaysia. This study was done via of literature review, questionnaire survey and expert focus group for data validation. This study found that: (1) the existing practice shows that the project management team for cost control in residential construction project in Malaysia are the moderate implementation of proper tendering system and bidding process, weak tender committee enforcement on the cost comparison for every contract awarded in a project and no submission of the project cost report to management throughout the project; (2) the cost overrun in residential construction project was causes by improper planning and scheduling, inconsistency in material?s price, incompetent contractor, and poor financial capabilities by contractor; (3) the improvement measures of the cost overrun in residential construction project in Malaysia of which include effective project planning and scheduling, having competent project management teams and using cost-saving construction method in the project. This study could serve as a guideline to the project management team, which involves in Malaysia residential construction project to maximise the cost performance in the project and thus shall support the Construction Industry Transformation Programme Malaysia's national agenda.
Item Type: | Thesis (Masters) |
---|---|
Additional Information: | Thesis (Sarjana Kejuruteraan (Pengurusan Pembinaan)) - Universiti Teknologi Malaysia, 2020; Supervisors : Assoc. Prof. Ts. Ir. Dr. Syuhaida Ismail |
Uncontrolled Keywords: | causes of cost overrun, cost control, improvement measures, residential construction project, Malaysia |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
Divisions: | Civil Engineering |
ID Code: | 92797 |
Deposited By: | Yanti Mohd Shah |
Deposited On: | 28 Oct 2021 10:26 |
Last Modified: | 28 Oct 2021 10:26 |
Repository Staff Only: item control page